Good morning, Adaeze
6 active programmes · 20 tracked risks · 2 critical · updated 12 min ago
Portfolio holding at 72/100, but momentum is deteriorating on 1 programme driven by tunnelling slip in Lagos and MEP rework in Manila. Single-source signaling exposure remains the highest unmitigated risk. KAIRN flagged 5 emerging signals in the last 14 days — recommended actions are queued for executive approval.
3
Within tolerance
2
Watchlist — intervention recommended
1
Executive escalation
Critical path
Severe risk
100
Exposure index
5
open items
Avg slip +23d · TBM advance & MEP rework dominating slack consumption
Procurement
Elevated risk
59
Exposure index
2
open items
Single-source signaling vendor in distress · Q3 asphalt supply constrained
Stakeholder
Elevated risk
63
Exposure index
4
open items
Mushin community pushback · donor reporting alignment improving
Overall portfolio health
Weighted across 6 programmes
+2 vs last week
Emerging risks
5
trending up this week
Critical risks
2
across portfolio
Top 5 emerging risks
Detected last 14 days- ViewcriticalScope
MEP coordination clashes on Block C
Manila Regional Hospital Complex · Owner: R. Santos
- ViewcriticalProcurement
Signaling subcontractor financial distress
Lagos Metro Line 3 · Owner: S. Patel
- ViewhighSchedule
Tunnel boring delay at Yaba segment
Lagos Metro Line 3 · Owner: A. Okonkwo
- ViewhighGeopolitical
Security clearance for field teams — Mali
Sahel Climate Adaptation Fund · Owner: F. Diallo
- ViewhighCost
FX exposure on imported rolling stock
Lagos Metro Line 3 · Owner: M. Adeyemi
Risk heat map
Likelihood × Impact (count per cell)
Risk evolution — last 12 weeks
Open risks stacked by severity
Programme health — last 12 weeks
Per-programme health score trajectory
Recommended actions
Highest impact · openPre-qualify backup signaling vendor
Lagos Metro Line 3 · S. Patel · Due 2026-06-21
Impact: HighEffort: MediumIn progressExecute FX hedge on EUR exposure
Lagos Metro Line 3 · M. Adeyemi · Due 2026-06-14
Impact: HighEffort: LowNot startedRe-baseline TBM advance schedule
Lagos Metro Line 3 · A. Okonkwo · Due 2026-06-30
Impact: HighEffort: HighNot startedAccelerate translocation programme
A14 Eastern Expansion · R. Hughes · Due 2026-06-20
Impact: HighEffort: MediumIn progressActivate remote monitoring protocol
Sahel Climate Adaptation Fund · F. Diallo · Due 2026-07-01
Impact: HighEffort: MediumIn progressBIM clash resolution sprint
Manila Regional Hospital Complex · R. Santos · Due 2026-06-16
Impact: HighEffort: HighIn progress
Programmes
RAG status by weighted health score
| Status | Programme | Sector | Phase | Health | Risks | Schedule var. | Updated |
|---|---|---|---|---|---|---|---|
| At risk | Lagos Metro Line 3 Lagos State Government · Lagos, Nigeria | Infrastructure | Execution | 62 | 6 | +42d | 2 hours ago |
| On track | Nairobi Water Resilience Programme World Bank / Athi Water · Nairobi, Kenya | International Development | Execution | 78 | 3 | +12d | 1 day ago |
| At risk | A14 Eastern Expansion National Highways UK · Cambridgeshire, UK | Infrastructure | Execution | 71 | 4 | +21d | 5 hours ago |
| On track | Sahel Climate Adaptation Fund UNDP / AfDB · Burkina Faso, Mali, Niger | International Development | Planning | 84 | 2 | 0d | 3 days ago |
| On track | Riyadh Suburban Rail Phase 2 Royal Commission for Riyadh · Riyadh, Saudi Arabia | Infrastructure | Planning | 81 | 2 | +6d | 2 days ago |
| Off track | Manila Regional Hospital Complex Department of Health, Philippines · Metro Manila, Philippines | Construction | Execution | 54 | 3 | +56d | 6 hours ago |