Lagos State Government·Lagos, Nigeria·Infrastructure

Lagos Metro Line 3

Phase: ExecutionBudget: $1.42BCost var: +7.2%Schedule var: +42d
62of 100

Project health

+1 vs last week

Upload project documents

Progress reports, risk registers, schedules, correspondence — PDF, DOCX, XLSX up to 50 MB.

Top risks on this programme

  • highSchedule

    Tunnel boring delay at Yaba segment

    TBM advance rate dropped 38% over the last 3 weeks, threatening Q3 station handover milestone.

  • highCost

    FX exposure on imported rolling stock

    EUR/NGN movement implies $48M unbudgeted exposure on remaining drawdowns.

  • criticalProcurement

    Signaling subcontractor financial distress

    Single-source signaling vendor showing distress signals; no qualified alternative pre-positioned.

  • mediumStakeholder

    Community resettlement pushback — Mushin

    Community association formally objected; risk of injunction if not resolved within 6 weeks.

Key metrics

Risks tracked
6
Open actions
5
Documents analyzed
5
Last analysis
2 hours ago

Recent activity

  • KAIRN re-scored programme health (+1) · 2h ago
  • 2 new emerging risks detected · 6h ago
  • Risk register v14 ingested · 1d ago
  • Action "Pre-qualify backup vendor" moved to In progress · 1d ago